SolarEdge (Modbus) smart home integration, free and open source

SolarEdge (Modbus) integration for Gladys Assistant

Local SolarEdge inverters, meters and batteries over Modbus TCP, no cloud.

This integration connects Gladys to your SolarEdge installation locally, over Modbus TCP: no SolarEdge account, no cloud, no API key, and a reading every few seconds instead of every 15 minutes.

What you get​

The integration detects everything that answers behind your inverter:

DeviceFeatures
Inverter (each one)Solar production (W), total production (kWh), AC voltage, AC current, heat sink temperature, status
Grid meterGrid power (W, import > 0, export < 0), import index (kWh), export index (kWh), house consumption (W)
Consumption meterHouse consumption (W), consumption index (kWh)
Battery (StorEdge)Charge level (%), charge power, discharge power (W), charged / discharged energy (kWh), available energy (kWh), temperature, status

The house consumption is computed from the production of the inverters and the grid exchange. The indexes feed the Gladys energy dashboard.

Before you start: enable Modbus TCP​

  1. Open the SetApp application next to the inverter (or the LCD menu on older inverters): Commissioning → Site Communication → Modbus TCP → Enable.
  2. Note the port: 1502 by default on SetApp inverters, often 502 on older ones.
  3. Give the inverter a fixed IP address in your router (DHCP reservation).
  4. Modbus TCP works over the Ethernet port of the inverter. Over Wi-Fi it depends on the model and firmware.

The inverter accepts a single Modbus TCP client at a time. If another system (Home Assistant, an energy manager…) already reads it over Modbus, stop it, or the two will kick each other out.

Configuration​

FieldDescription
Inverter IP addressThe address of the inverter (the leader one with several inverters).
Modbus TCP port1502 by default.
Modbus unit ids1 for a single inverter. Leader/follower installations: every inverter's id, comma separated (e.g. 1,2).
Refresh intervalSeconds between two reads (5 to 300, 10 by default). Large installations are automatically slowed down.
Solar surplus thresholdGrid export (W) above which the Solar surplus trigger fires (500 W by default).
Invert the grid meter directionTurn on if Gladys shows an import while you export.
Allow inverter controlOff by default: the integration only reads. Turn on to let scenes and widgets limit production or drive the battery.

Save, then click Test the connection: the integration lists what it found and the devices appear in the Discovery tab, ready to be added.

Scenes​

Triggers​

  • Inverter status changed — producing, limited, sleeping (night), fault… Filter on the inverter and the new status. Variables: status, previous_status, power.
  • Solar surplus — the grid export goes above the threshold (started) or falls back below half of it (ended). Ideal to start a water heater, a pool pump or an EV charge. Variables: state, export_power.
  • Battery status changed — charging, discharging, idle, fault… Variables: status, previous_status, level.
  • Inverter connection lost or restored — after 3 failed reads in a row. Variables: state, message.

The standard Gladys "device state" trigger also works on every feature (e.g. battery level above 90 %, production above 2000 W).

Actions​

  • Read the solar installation — returns production, consumption, grid power, battery level, today's production and inverter status to the next actions (conditions, notification texts…).
  • Limit the solar production — active power limit in % of the nominal power, for instance during negative prices. 100 removes the limit. The limit stays stored in the inverter until it is changed again.
  • Set the battery mode — maximize self-consumption, time of use, backup only, remote control.
  • Charge or discharge the battery — a remote command (charge from solar and grid, discharge to cover the house, hold…) for a given duration, with an optional power limit. Then the inverter returns to its default mode.
  • Set the backup reserve — share of the battery kept for power outages.

The control actions require Allow inverter control in the configuration. Otherwise they return applied = false without touching the inverter. Battery commands require a StorEdge inverter; charging from the grid may also require the "AC charge" policy enabled by your installer.

Dashboard​

  • Solar production — live production, consumption, grid exchange and battery level, a production chart (period configurable), today's production, the inverter status and your self-sufficiency.
  • Solar battery — charge level, charge and discharge power, available energy, status, health, mode and backup reserve. When control is allowed, two buttons switch the battery to self-consumption or backup only.

Configuration screen buttons​

  • Test the connection — detects the installation and refreshes the devices.
  • Remove the production limit — sets every inverter back to 100 %.

Troubleshooting​

  • "Cannot reach…": check the IP address and the port, that Modbus TCP is enabled, and that no other Modbus client is connected.
  • Exception 11 / no answer on unit id: the unit id is wrong. Single inverters use 1.
  • Grid power with the wrong sign: turn on Invert the grid meter direction.
  • Today's production starts from the first reading of the day (local time of the integration) and survives restarts.
  • At night most inverters keep answering in sleeping mode; some stop answering: the devices stay in Gladys and come back at sunrise.
  • Logs: open the integration logs in Gladys. Set LOG_LEVEL=debug for details.

Configuration settings​

These are the settings SolarEdge (Modbus) asks for in its configuration screen in Gladys.

SettingTypeRequiredDescription
Enable Modbus TCP on the invertersectionNoIn the SetApp application (or the LCD menu of older inverters): Commissioning > Site Communication > Modbus TCP > Enable. Note the port (1502 by default) and give the inverter a fixed IP address on your router. The inverter accepts a single Modbus client at a time.
Inverter IP addressstringYesIP address or host name of the inverter (the leader one with several inverters).
Modbus TCP portnumberYes1502 on SetApp inverters, often 502 on older ones.
Modbus unit idsstringNo1 for a single inverter. Leader/follower installations: the ids of every inverter, comma separated (e.g. 1,2).
Refresh interval (s)numberNoSeconds between two reads of the whole installation (5 to 300).
Solar surplus threshold (W)numberNoGrid export above which the "Solar surplus" scene trigger fires. It ends below half of it.
Invert the grid meter directionbooleanNoTurn on if Gladys shows an import while you export (meter installed the other way round).
Allow inverter controlbooleanNoLets scenes and widgets write to the inverter: production limit, battery mode and commands. Off: read only.

How to install SolarEdge (Modbus) in Gladys​

  1. In Gladys, open Integrations: SolarEdge (Modbus) appears in the catalog, next to the native integrations, with a community badge.
  2. Click Install. Gladys pulls the Docker image (ghcr.io/gboulvin/gladys-solaredge-modbus:1.0.1), starts it in a sandbox isolated from the core, and generates the integration's interface (devices, discovery and configuration).
  3. Open the Configuration screen of the integration, fill in the settings, and save.
  4. You can also install it directly from its repository URL: https://github.com/gboulvin/Gladys-SolarEdge-ModBus.

SolarEdge (Modbus) requires Gladys >=5.1.0. The catalog inside Gladys refreshes every hour, so a new version becomes available at most one hour after its release.

Not running Gladys yet? It is free and open source: follow the installation guide to get started.

About external integrations​

SolarEdge (Modbus) is an external integration: a community integration packaged as a Docker container and published on GitHub, that Gladys installs in one click and runs in a sandbox isolated from its core. It is published and maintained by gboulvin, not by the Gladys core team.

Subscribe to the Gladys Assistant newsletter